- Home
- Departments
- Highway Department
- Current Highway Projects
Current Highway Projects
Project Map (PDF)
Project List
#1 – Re-Construction of CSAH 15
Location: On CSAH 15 from the west county line (Minnesota River) for 2.75 miles east to approximately Minnesota River Drive SW
Description: Grading, drainage and aggregate base
Contractor: Kern & Tabery from Wadena, MN
Approximate Start: June 2022
Approximate Finish: November 2022
Detour: See Map (PDF)
Project Update(s): Contractor scheduled to begin work in July
Public Meeting May 23, 2022 (PDF)
7/14/2022 Update: Constructed scheduled to begin July 25, 2022
7/20/2022: Press Release (PDF) Road Construction Begins July 25, 2022.
8/3/2022: NOTICE: Temporary Mailbox Relocation
10/24/2022: Project Update
#2 – Re-Construction of CSAH 30
Location: On CSAH 30 from the north county line for approximately 2.75 miles south
Description: Grading, drainage and aggregate base
Contractor: Kern & Tabery from Wadena, MN
Approximate Start: June 2022
Approximate Finish: November 2022
Project Update(s): Contractor scheduled to begin work in June
Public Meeting May 23, 2022 (PDF)
7/14/2022 Update: Construction began June 1, 2022. Contractor scheduled to complete earthwork operations by end of July, weather depending.
8/15/2022 UPDATE: The Contractor has completed the work. Paving will be in 2023.
#3 – Mill and Overlay of CSAH 16
Location: On CSAH 16 from CSAH 5 to CSAH 15 (approximately 8 miles)
Description: Milling and new bituminous pavement
Contractor: Central Specialties, Inc. from Alexandria, MN
Approximate Start: September 2022
Approximate Finish: October 2022
Project Update(s): Update 9/12/2022: The Contractor will begin milling on CSAH 4 on 9/12/2022. Milling operations anticipated the week of 9/12 and 9/19.
Update 10/24/2022: The Contractor has completed the project on October 14, 2022.
#4 – Mill and Overlay of CSAH 4
Location: On CSAH 4 from TH 7 to N City Limits of Maynard & from TH 23 to south county line
Description: Leveling course, underseal, milling and new bituminous pavement
Contractor: Central Specialties, Inc. from Alexandria, MN
Approximate Start: September 2022
Approximate Finish: October 2022
Project Update(s): UPDATE 9/9/2022: The Contractor is scheduled to begin milling on CSAH 4 on 9/12/2022 starting at the south county line and working north. Expect delays when traveling through construction zones.
Update 10/24/2022: The Contractor has completed the project on October 14, 2022.
#5 – Seal Coating
Location: Wegdahl Bike Trail, CSAH 21 (Milan), CSAH 9 (Watson), CSAH 42 (Montevideo), CSAH 5 (Granite Falls), CSAH 38 (Granite Falls)
Description: Application of seal coat material
Contractor: Gee Asphalt Systems, Inc. from Cedar Rapids, IA
Approximate Start: Late August
Approximate Finish: Mid-September 2022
Project Update(s): UPDATE 9/6/2022: Start date is scheduled for September 13, 2022, weather depending. Work is scheduled to begin in Milan.
Update 10/24/2022: The Contractor has completed the work in Milan, Watson, Montevideo streets. The Contractor will be back in early summer of 2023 to complete seal coating in Granite Falls and on the Wegdahl Bike Trail.
#6 – Aggregate Surfacing
Location: CSAH 5, CSAH 7, and CSAH 12
Description: Crushing, Hauling and Placing Class 5 Gravel Aggregate
Contractor: Wm. D. Scepaniak Inc. from Holdingford, MN
Approximate Start: August 2022
Approximate Finish: September 2022
Project Update(s): UPDATE 8/19/2022: Contractor scheduled to begin the week of August 29, 2022.
UPDATE 9/6/2022: Contractor began crushing 8/29/2022. Hauling and placing anticipated the week of September 5, 2022.
UPDATE 9/12/2022: The Contractor is scheduled to begin hauling and placing gravel starting on 9/13/2022.
UPDATE 10/24/2022: The Contractor has completed this project.
#7 – Replace Bridges
Location: On CSAH 12 approximately 1/4 mile east of the intersection of CSAH 12 & CSAH 6 and on CSAH 12 approximately 1/4 mile west of the intersection of CSAH 12 and 20th Ave NW
Description: Replacement of timber bridges with new concrete box culverts
Contractor: Riley Brothers Construction from Morris, MN
Approximate Start: Estimated Start date is 8/29/2022
Approximate Finish: Mid September 2022
Project Update(s): 8/12/2022 UPDATE: Contractor is scheduled to begin construction around August 29, 2022.
8/19/2022 UPDATE: The Contractor moved up the start date and started construction on August 19, 2022.
9/6/2022 UPDATE: The Contractor completed the bridge on CSAH 12 located approximately 1//4 mile west of the intersection of CSAH 12 & 20th Ave NW. Work began on the second bridge on 9/1/2022.
10/24/2022 UPDATE: Both Bridges have been completed.
#8 – Pavement Marking
Location: County Wide
Description: marking of centerline and edge lines on county roads
Contractor: Sir Lines-A-Lot from Edina, MN
Approximate Start: September 2022
Approximate Finish: October 2022
Project Update(s): 10/24/2022: The Contractor has completed the pavement markings on October 17, 2022.
#9 – CSAH 16 Railroad Crossing (Not shown on the map)
Location: Between US 212 and CSAH 16
Description: installation of a new concrete panel crossing and paving about 300 feet of CSAH 16
Contractor: Joe Riley Construction from Morris, MN
Approximate Start: August 10, 2022
Approximate Finish: August 19, 2022
Project Update(s): 8/17/2022: The project was completed on 8/15/2022.